Client: Stocker Yale
Project: New Facility
Project Type: Design/Build
Industry: Research & Development
Project Highlights
- New research & development facility adjacent to existing 80,000 SF plant and corporate offices
- 10,000 SF steel frame addition
- 4,000 SF of class 1 office space
- 6,000 SF of class 1 lab space
- Constructed a high-bay fiber draw tower space
- Constructed laboratories and test areas
- Chemical storage bunkers
- Approximate Value: $4,384,000
- 4 story high fiber optic draw tower
- Hodess used the gas bunker built during Phase I to tie into utilities
- Design/Build
- Architect: SMRT
Similar Hodess Projects
- Fairchild Semiconductor, Portland, ME
- Brown University, Barrus & Holley Microelectronic Center, Providence, RI
- RF Micro Devices Fab II Phase I, Greensboro, NC
- Digital Equipment Corp. Fab 4 Annex Phase 1-3, Hudson, MA
- Nortel (formerly Coretek), Wilmington, MA
- Insight Technology, Londonderry, NH
- Solasta, Newton, MA
- Teradyne Composite Cleanroom, Nashua, NH
- University of Rhode Island Aquaculture Science Laboratory, Kingston, RI
- BAE Microwave East Cleanroom Upgrade, Nashua, NH
- Filtrona Extrusion Cleanroom Expansion, Athol, MA
- Teradyne Northeast Blvd., Nashua, NH
- Polyclad Corporation, Franklin, NH
- AmberWave, Salem, NH
- National Semiconductor Building 18, Portland, ME