Client: R.F. Micro Devices
Project: Fab II Phase I
Project Type: New Construction
Industry: Research and Development
Project Highlights
- Size: 40,000 sf
- 20,000 sf of cleanroom from Class 100 – Class 10,000
- 10,000 sf of lab and 10,000 sf of mechanical/electrical support space
- Structural steel mezzanine above the entire cleanroom area
- Supplied recirculation units, 1,000 KW emergency generator and 2 400-ton chillers
- Fast track 20 week project
- Value: $13,400,000
- Construction Manager
- Designer: CRB
Similar Hodess Projects
- BAE Systems IR Common Build Phase II, Nashua, NH
- Axcelis CCS Manufacturing, Beverly, MA
- AmberWave, Salem, NH
- Teradyne Composite Cleanroom, Nashua, NH
- Rohm and Hass (formerly Shipley), Marlboro, MA
- Teradyne TCO Cleanroom, Nashua, NH
- Filtrona Extrusion Cleanroom Expansion, Athol, MA
- Ahura, Wilmington, MA
- Teradyne Northeast Blvd., Nashua, NH
- Millipore Mobius II, Danvers, MA
- SVG Lithography, Multiple Projects, Ridgefield and Wilton, CT
- Vascular Technology, Nashua, NH
- Unitrode Fab III, Merrimack, NH
- BAE System Microelectronic Center for Excellence, Nashua, NH
- Brown University Metcalf Labs, Providence, RI